GL SYSTEM FULL BOND INSTALLATION
Wall Preparation
Ensure that the wall is dry and free of cement lumps, dust, and grease. A rough surface is preferable.
Marking Mark
Ensure the desired final thickness by using marking and laser guidance.
Combining Ingredients
Combine GL Bond with clean water in a 2:1 ratio and stir until the mixture perfectly.
Application of GL Bond: First Layer
Apply GL Bond to the wall, covering an area the size of one installed gypsum board, using a flat roskam.
Apply a second layer of GL Bond.
Apply an additional layer of GL Bond to the previously treated area using a serrated roller.
Gypsum Board Installation
- Ensure the gypsum board is installed evenly
- A distance of 10 mm from the floor should be maintained by providing proper anchoring.