GL SYSTEM FULL BOND INSTALLATION

Wall Preparation

Ensure that the wall is dry and free from cement lumps, dust, and grease. A rough surface is preferable.

Marking Mark
Ensure the desired final thickness using marking and laser guidance.

Combining Ingredients
Put together GL Bond with clean water in a 2:1 ratio, stir until the mixture perfectly.

Application of GL Bond: First Layer
Apply GL Bond to the wall, covering an area to the size of one installed gypsum board, using a flat roskam.

Apply a second layer of GL Bond.
Add an additional layer of GL Bond using a serrated roller in the previous GL Bond area.

Gypsum Board Installation

  • Ensure the gypsum board is installed evenly.
  • A distance of 10 mm from the floor by providing proper anchoring.